TOKYO — Boeing expects commercial flights of its grounded 787 jets resuming “within weeks” even though it has not pinpointed the cause of battery overheating.

Boeing Co. Chief Project Engineer Michael Sinnett outlined a fix centred on a new design for the lithium-ion battery system that has layers of safeguards to prevent overheating and measures to contain malfunctions.

A third of safety tests have already been completed. A Japanese official said it was possible flights could resume next month.

The 787 fleet was grounded worldwide by the US Federal Aviation Administration, its counterparts in Japan and other nations in January, following a battery fire in a Dreamliner parked in Boston and an overheated battery that led to an emergency landing of another 787 in Japan.

The Dreamliner is the first airliner to make wide use of lithium-ion batteries. They are light and quick to charge but can suffer from “thermal runaway,” a chemical reaction in which a rise in temperature causes a spiral of temperature increases. Executives said it would take too long to figure out what had specifically caused the problems in Boston and southwestern Japan but the new design would ensure 787s are safe.

Boeing came up with 80 possible causes for the battery failures, categorized them into four groups, and came up with design changes such as better insulation between each battery cell so any malfunctions won’t spread. That was to allow the 787 to be back in the air more promptly, they said.

There were also changes to wiring for the battery, aimed at preventing overheating, and a new enclosure for the battery that they said would eliminate fire risk.

The enclosure has a direct vent to carry battery vapours outside the airplane, and small holes at the bottom of the battery case will allow moisture to drain from the battery, according to Boeing. The battery charger is also being adapted to beef up safety, it said.

While executives acknowledged that final approval would have to come from the FAA, and didn’t rule out further delays to ensure safety, they said they were in close contact with the FAA and didn’t foresee any long delays.

“It’s a safe airplane. We have no concerns at all about that,” Sinnett said.

Boeing Executive Vice-President Ray Conner offered his apologies to Japan for the problems.

“We do apologize for this situation,” Conner said. He said he was in Japan to meet with aviation authorities and airlines, and the company had picked Japan as the place to outline the battery fix.

About a third of the plane is made by Japanese manufacturers, including GS Yuasa, which supplies the lithium-ion batteries.